Expanding Road Construction site with D&S technology

Recently the blogger visited a rock work site in the siuthern peninsula, Korea.
They were using all kinds of equipments( excavator, rock drill rig, a hydraulic rock splitter of 4  cylinders). The road was narrow and expansion was planned by local authority.
The construction company attempted to use D&B( blasting) method. But the neighboring residents protested against this blasting and the company had to use hydraulic demolition method.
               

       
Drilling was made with spacing of 60cm,  vertically.
 They are using hand-held splitters of  4  x 95mm cylinders.

 A series of rock splitting equipments are engaged.  An excavator, a crawler rock drill rig, and a set of 4 splitters manual type .

Special remarks:


This kind of work site has very low efficiency in rock splitting because of bottle neck in drilling .  Each rock hole of 1000mm deep drilling  takes average 2minutes. It means  4 holes take time of 8 minutes in drilling.

Rock splitting ( or fracturing) takes 2~3 minutes average per cycle with 4 splitters.

An excavator is used  for a short while for mucking the rubble.

In other words, splitters and excavator is not fully utilized because of rock drilling time.

We recommend 3 rock drill rigs and 2 Splitter sets of 6 splitters ( manual type) or a set of 4 splitters of 6 splitters( machine -mounted) and an excavator.